Inquiry timeline

Board of Inquiry timeline

  • 18 March 2025

    Order in Council made establishing the Board of Inquiry.

  • 7 May 2025

    Public hearings commenced.

  • 20 - 24 June 2025

    Second public hearing block.

  • 21 July 2025

    Final date for each of the experts engaged by the Inquiry, the Mornington Peninsula Shire Council and South East Water to provide to the Inquiry their own report containing their opinion as to the cause of the McCrae landslide (Experts).

  • 4 & 5 August 2025

    Public hearings at which the Experts will give oral evidence about the cause of the McCrae landslide.

  • 12 August 2025

    Final date for the Experts to provide to the Inquiry their own report containing their opinion as to the measures required to prevent or reduce the risk of a further landslide.

  • 18 August 2025

    Final public hearing at which Experts will give oral evidence about the measures required to prevent or reduce the risk of a further landslide.

  • 10 September 2025

    Final date for the Board of Inquiry to provide a report of findings and recommendations to the Governor of Victoria.

Updated